The mechanical engineer Yoel Abreu Rivero, director of maintenance of this industry and at the head of the ambitious work, said that the investment is a cardinal repair that normally is realized every ten years, although he clarified that the development excess over this time spoiled the technical indicators.

In economic terms this project is valued for nearly 56 million pesos with a real payment for the year of 47 millions, pointed out the source, who added that the work regime comprises double shift of 8 hours and in the critical route it spreads to 24 hours.

He told that it forces the entry of a third shift at 12:00 p.m. that checks the badges of the works realized by the other two groups.

An imposing iron mass is the block number six. Imagine that the cauldron weights near the 1 000 tons and the number of workpeople that participate in the different shifts of nears 740, of them 42 forms the investment group, with a high qualification, while the least trained need a high knowledge level to face this type of maintenance.

Translated by BA in English Language, Manuel Barrera Téllez