We repair well the plant so that it works without big mishaps in the grinding, said Ania Ricardo Leyva, head of the Room of Control and Analysis of the plant.

The works that they realize in the factory are developed in accordance with the timetable, which indicates that the "Siboney" will be ready for the sake of doing tests with sufficient time, and this way correcting any flaw, the specialist ensured.

In this moment the principal effort goes to the assembly of the mills in the tandem and of the devices of the so-called house of cauldrons, where the making of the sugar closes.

This plant has tentatively to kick off the grinding of the cane on December 1st and to operate for 139 days, until the middle of April, 2016.

Industry of major stability in the processing of raw material, indicators of efficiency and integral outcomes of Camagüey, the "Siboney" will be supplied from nearby plantations and others located in areas of the Panama plant, to over 50 kilometers by train.